Clay – Edic and DeWitt Substation Upgrades
Owner: NGRID
Client: MJ Electric
Value: $8 million dollars.
Multiple phase rebuild of multiple 345kV substations in 22 months that are key to the reliable supply of power to New York City – provided forensic project management to assess status, developed a simple streamlined cost-to-complete (CTC) and schedule forecasting process linked directly to daily time & quantity reporting as part of the “GO FORWARD PLAN” to track productivity, forecast costs, identify opportunities to improve & control costs, and mitigate margin loss.